| Event |
Date |
 |
| VIJAYAWADA 500 MW - Boiler Hydraulic test successfully completed on 28.12.07 |
28/12/2007 |
| JSL Unit-1 : Coal firing had been successfully done at 0245 HRS on 16.12.07 with Mill-A in service and loaded to 20MW |
16/12/2007 |
| RAICHUR 250 MW UNIT – 8 : Boiler Erection Commenced on 12.12.07. First Column of Boiler (S5R) was erected at 10.00 HRS on 12th Dec 07 |
12/12/2007 |
View |
| KRL KOCHI : Commencement of Civil Works on 10/12/2007 |
10/12/2007 |
View |
| BELLARY 1 X 500 MW : was synchronised on oil firing at 20:44 Hrs on 03.12.07. Maximum load reached was 67 MW. |
03/12/2007 |
View |