| Event |
Date |
 |
| JSL Duburi Unit 2 : Boiler lighted up at 20.42 Hrs on 30th Mar.2008 |
30/03/2008 |
| DAMANJODI : Generator Lifted on 27/03/08 at 07:30 PM |
27/03/2008 |
| BELLARY UNIT -1 500 MW : Coal Firing was achieved for first time at 19.15 Hrs on 25.03.08 with two mills in the presence of senior officials of KPCL and BHEL and the load was raised to 60 MW |
25/03/2008 |
View |
| CPCL-Manali : GT-3 put on RACHETTING thro MARK-VI at 23.50 hrs on 14th March 2008 |
14/03/2008 |
| RTPP Stage II - Unit-IV - - FULL LOAD Operation Commenced at 10.00 HRS on 13th Mar.2008. It had Successfully completed 24 HRS Operation & Continues to run on FULL LOAD |
13/03/2008 |
| JSL 2 X125 MW - Unit II Boiler Hydraulic Test at 237 KG/SQCM - (Drainable and Non-Drainable) successfully completed in the presence of both Director & Asst. Director / Boilers and Factories, Orissa. |
04/03/2008 |